Newest Viewed Downloaded

4E1 Project Management Costing – 2 Marginal Costing, ABC and Depreciation

4E1 Project Management Costing – 2 Marginal Costing, ABC and Depreciation

Key Concepts

Marginal/decision costing Sunk costs and other excluded costs Activity-based costing Calculating labour and machine costs Depreciation and amortisation

Marginal (Decision) Costing

Also known as variable, direct and decision costing Basic principle: cost = direct costs only Direct costs: Salaries/wages Raw materials Plant hire Other costs are generally omitted: Overheads Money spent before the project starts (“sunk costs”) Indirect costs

Marginal Costing Example

4,000 4,000 4,000 4,000 4,000 Overhead                 5,400 3,400 7,200 10,500 11,000 Subtotal   600 600 3,000 6,000 5,000 Materials   4,800 2,800 4,200 4,500 6,000 Labour cost   32 28 28 30 30 Rate/hour   150 100 150 150 200 Labour hours Project 2               4,025 2,025 3,500 3,700 3,500 Total Cost   2,000 - 1,000 1,200 1,000 Materials   2,025 2,025 2,500 2,500 2,500 Labour cost   27 27 25 25 25 Rate/hour   75 75 100 100 100 Labour hours Project 1 5 4 3 2 1     Period     Marginal costing is usually (though not always) straightforward. Unlike the previous example, we simply ignore overheads.

Marginal Costing: Pros & Cons

Advantages Simple Data relatively easy to collect or estimate Easy to compute Avoids allocation problem Forward-looking Tends to be less controversial with users Avoids distortions due to incorrect absorption Disadvantages Ignores many realities, e.g. Sunk costs Indirect and knock-on costs Understates the true cost Can lead to bad decisions e.g. “throwing good money after bad”

Marginal Cost: Weaknesses

Startup/ Preacquisition Costs Post completion Costs Secondary Costs Disruption Costs Opportunity Costs Displacement Costs Start Finish Marginal Cost

Activity-Based Costing

Basic principle: cost = direct cost + indirect driven cost Overhead is allocated according to: labour hours/costs machine hours/costs materials cost direct costs ABC is offered as more accurate/meaningful A better basis for decisions

ABC Versus Absorption

€75.00 €47.50 Cost/unit €25.00 €12.50 Per unit €37,500 €12,500 Overhead allocation 1,500 500 Hours Overhead €50,000 Labour cost/hour €20 1.0 0.5 Labour hour/unit 30 25 Materials/unit (€) 1,500 1,000 Units Y X Illustration using an industrial example A company produces two products X and Y Using traditional cost accounting:

ABC Versus Absorption

Number of customers for product € 5,000 Packaging Time required to clean after production €10,000 Plant cleaning Number of inspections €25,000 Quality inspections Number of set-ups €10,000 Machine set-ups Cost driver Cost Task ABC considers what drives the overheads Assume these are made up as follows: The following data are gathered:

ABC Versus Absorption

75.00 47.50 Absorption cost/unit 60.33 69.50 Cost per unit 10.33 34.50 Per unit 1,500 1,000 Units 15,500 34,500 Total 4,000 4 1,000 1 1,000 Packaging 2,000 2 8,000 8 1,000 Cleaning 7,500 3 17,500 7 2,500 Inspections 2,000 1 8,000 4 2,000 Set-ups ABC (€) Product Y ABC (€) Product X Cost (€) Activity

Costing Detail: People

Important to cost labour accurately e.g. how much does an engineer cost per hour? Total cost includes: Salary Social welfare cost Pension cost Office costs (if relevant) Other non-people support costs Training, etc. We also need to know time worked, based on: Standard hours per year Non-working time: holidays, training time, illness, etc.

Costing People - Example

Joe is paid €36,400 p.a. and works a 35-hour week (1,820 hours/year) Gives an hourly cost of €20 But: Joe’s pension, social welfare and perks add another €4,000 Joe works only 1,155 hours a year 4 weeks annual leave plus 10 days of public holiday one week’s sick leave one week’s training and Joe effectively works about 6 hours in every 8 1155 hours @ €40,400 ≈ €35 per working hour

Costing Detail: Machine Hire

Maximum time available Planned time available Available time Normal time available Not worked Planned running time Changeovers Actual running time Machine down time Obviously, this does not matter if it is a fixed cost.

Depreciation/Amortisation

Rationale Assets cost money Physical assets will be used up through wear and tear, depletion, loss of value, etc. This usage is known as: “depreciation” (for equipment) “amortisation” (for wasting assets e.g. mines, quarries) Basic methods: Straight line Declining balance Sum of digits Double declining balance

Plant and Machinery Costing

Total cost Depreciation Maintenance

Straight Line Depreciation

€ 0 €50,000 4 € 50,000 €50,000 3 €100,000 €50,000 2 €150,000 €50,000 1 Balance Charge Year Based on no. years over which asset will be written off Machine press bought for €200,000, written off over 4 years Therefore, depreciation charge is 25% per year Pros: simple to compute; writes off assets cleanly (no residual balance problem) Cons: not always realistic

Declining Balance Depreciation

Year Charge Balance 1 €50,000 €150,000 2 €37,500 €112,500 3 €28,100 € 84,400 4 €21,100 € 63,300 Write off same % of residual balance each year press may be written off over infinite no. of years may therefore need a termination year e.g. write down press over 4 years at 25% p.a. Pros: relatively easy to compute; realistic for many assets Cons: Problem of residual balances

Sum of Digits Depreciation

€ 0 €20,000 4 € 20,000 €40,000 3 € 60,000 €60,000 2 €120,000 €80,000 1 Balance Charge Year Combines exponential and a clean write-down Example: assume 4-year write-down Add the digits in the no. of years: 1 + 2 + 3 + 4 = 10 Take the write-down in order: 4/10, 3/10, 2/10, 1/10 Pros: Approximates declining balance; no residual balance problem Cons: More complicated to compute

Double Declining Balance Depreciation

0 0 10 0 0 20,000 20,000 9 920 920 20,000 40,000 8 20,000 21,920 20,000 60,000 7 20,000 41,920 20,000 80,000 6 20,000 61,920 20,000 100,000 5 20,000 81,920 20,000 120,000 4 20,480 102,400 20,000 140,000 3 25,600 128,000 20,000 160,000 2 32,000 160,000 20,000 180,000 1 40,000 200,000 20,000 200,000 0 Charge Balance Charge Balance Year DDB SL Start with a straight line (say four years) Compute % depreciated (10%) and double it (20%) Depreciate with declining balance method at this rate until charge is less that it would be using straight line Use straight line value from there on

Shared Costs

Costs shared with other activities e.g. Machines used part of the time Part-time staff Shared overheads e.g. Management Insurance Not always clear how to account for shared costs

Showing 1 - 20 of 23 items Details

Name: 
L11 Costing 2
Author: 
Dept. of Statistics
Company: 
N/A
Description: 
4E1 Project Management Costing – 2 Marginal Costing, ABC and Depreciation
Tags: 
000 | cost | costs | 500 | and | costing | time | balance
Created: 
11/8/1996 8:19:58 AM
Slides: 
23
Views: 
1
Downloads: 
0
Rating: 
0


> Comment



Share this presentation
|

Comments

Share this presentation:

|
Sitemap